Oz Minerals Carrapateena Mine

Client

Oz Minerals

Time

4 Weeks

Services Provided

Design
Manufacture
Installation
Commissioning
Project Management

Location

Carrapateena

The Carrapateena mine is a large copper mine under development 100km southeast of Olympic Dam in South Australia’s Far North region.

Jaymel was approached by Oz Minerals to design and install a range of air conditioning systems for their facility in the Carrapateena Mine. Being in such a remote area of South Australia, approx. 500km from Adelaide, the main challenge for this project was distance, and ensuring that the design and project management was flawless to make sure installation was a smooth process. This was achieved by breaking the project down in stages.

Stage One
Design, draft, manufacture & deliver sheet metal ducting to site in rural South Australia. (Rough turnaround 3 weeks. 1 week planning, 2 weeks manufacturing)

Stage Two
Attend site and install sheet metal ducting including all associated grilles, supports, flashings and covers. Complete installation of under-ceiling cassette units. (6 day turn around)

Stage Three
Attend site and commission package systems and under-ceiling cassette units. (1 day per building)